Agency Information
Mission Statement
Directory
Calendar
Commission Agendas & Minutes
Consultant Selection
Items Open for Public Comment
Newsletter
Operating Criteria
Project Application Information
Send Us Your Comments
Planning Program
Dam and Reservoir Planning
Groundwater Grant Projects
Instream Flow Filings
Current Planning Projects
River Basin Planning
Weather Modification Study
Probable Maximum Precipitation
Water Research Projects
Construction Program
Current Construction Projects
Small Water Projects
Agency Publications
Project Reports
Water/Climate Web Atlas
Irrigation & Water System Surveys
Legislative Reports
Water Mgmnt & Conservation Dir
History of Wyoming Water Law
WWDC Home Page
Water Plan Home Page
WRDS Home Page
|
1996 LEGISLATIVE REPORT
Project Reports
82. | PROJECT: | Thayne Water Supply | | | | | |
| LEVEL: | I |
| SPONSOR: | Town of Thayne |
| LOCATION: | Lincoln County |
| PROGRAM: | New Development |
| |
| EXISTING LEGISLATION: |
|
Purpose |
Chapter |
Session |
Account |
Appropriation |
Due Date |
|
|
Level I |
8 |
1995 |
I |
$50,000 |
1996 |
|
PROJECT INFORMATION:
The Town supplies water to 150 taps. The water supply system consists
of a spring collection system which is pumped into a storage tank. The
tank is located on a hillside approximately one mile from the corporate
limits. The system cannot meet the present water demands including the
fire flow requirements. There are plans to construct a new secondary
school in town. Further, Thayne would like to expand through annexation
but cannot provide the water for the proposed expansion. The system may
need additional supply, transmission, and storage facilities.
Level I study served to inventory the existing system, evaluated water
supply needs, and evaluated water supply alternatives for the Town of
Thayne and the Bedford Water and Sewer District. Preliminary plans and
cost estimates were developed for the preferred alternative. The
proposed Level II study will include a water supply plan for the Town of
Thayne, the Bedford Water and Sewer District and Turnerville (the Willow
Creek Pipeline Company).
RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends that the project be advanced to Level II status with
an appropriation of $250,000.
|