Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
 Mission Statement
 Directory
 Calendar
 Commission Agendas & Minutes
 Consultant Selection
 Items Open for Public Comment
 Newsletter
 Operating Criteria
 Project Application Information
 Send Us Your Comments

Planning Program
 Dam and Reservoir Planning
 Groundwater Grant Projects
 Instream Flow Filings
 Current Planning Projects
 River Basin Planning
 Weather Modification Study
 Probable Maximum Precipitation
 Water Research Projects

Construction Program
 Current Construction Projects
 Small Water Projects

Agency Publications
 Project Reports
 Water/Climate Web Atlas
 Irrigation & Water System Surveys
 Legislative Reports
 Water Mgmnt & Conservation Dir
 History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

1997 LEGISLATIVE REPORT
Active Projects

 57. PROJECT:Middle Fork Dam
LEVEL:II-Hold
SPONSOR:State of Wyoming
LOCATION:Johnson County
PROGRAM:New Development
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level II 10 1994 I Hold   1996
Level II 15 1996 I Hold* 1998
*A block appropriation of $15,000 was made for all hold projects

PROJECT INFORMATION:
The proposed project would be located on the Middle Fork of the Powder River. The Middle Fork Reservoir would have a total capacity of 59,600 acre-feet, of which 47,700 acre-feet would be active storage for water supply and the remaining 11,900 acre-feet would be for the purposes of fisheries and recreation (minimum pool). The project would yield 32,200 acre-feet per year for industrial, agricultural and instream flow purposes. The project would cost approximately $55,000,000. In 1990, WWDC completed negotiations to obtain an interest in the reservoir permits from the Powder River Reservoir Corporation (PRRC). The transfer required a separate contract between EXXON U.S.A. and WWDC. EXXON has invested about 1.5 million dollars in the project and has a contract with the PRRC which had to be addressed before the state can proceed toward construction of the project. The Commission contracted with the USGS for a study of water quality parameters in the Powder River drainage. This report was completed in 1992. The WWDC will continue to monitor stream flows and water quality. Water quality is a key permitting issue.

RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends that the project be retained at Level II-Hold status.