Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
 Mission Statement
 Directory
 Calendar
 Commission Agendas & Minutes
 Consultant Selection
 Items Open for Public Comment
 Newsletter
 Operating Criteria
 Project Application Information
 Send Us Your Comments

Planning Program
 Dam and Reservoir Planning
 Groundwater Grant Projects
 Instream Flow Filings
 Current Planning Projects
 River Basin Planning
 Weather Modification Study
 Probable Maximum Precipitation
 Water Research Projects

Construction Program
 Current Construction Projects
 Small Water Projects

Agency Publications
 Project Reports
 Water/Climate Web Atlas
 Irrigation & Water System Surveys
 Legislative Reports
 Water Mgmnt & Conservation Dir
 History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

1997 LEGISLATIVE REPORT
Active Projects

 82. PROJECT:Sinclair Master Plan
LEVEL:II-Hold
SPONSOR:Town of Sinclair
LOCATION:Carbon
PROGRAM:New Development
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level I 10 1994 I $250,000   1996
Level II 15 1996 I Hold* 1998
*A block appropriation of $15,000 was made for all hold projects.

PROJECT INFORMATION:
The Town of Sinclair is an incorporated municipality with a population of 500. The water treatment and distribution system for the Town of Sinclair is operated by the Sinclair Refinery. The town has identified several deficiencies in their supply and distribution system. The existing 75,000 gallon tank was constructed in 1924 and is badly corroded. In 1993, the town requested funding for a water supply master plan to assess present/future needs and to evaluate the entire water system that was constructed seven decades ago. The Level I master plan has been completed. The project was delayed pending resolution of institutional issues between the Town of Sinclair, the Sinclair Refinery, and the City of Rawlins that has never been fully resolved. At a minimum, a new water storage facility with appurtenant piping and equipment is needed for Sinclair. The Sinclair Refinery may finance a significant portion of the needed improvements.

The master plan also evaluated potential improvements to the City of Rawlins' Fort Steele Pipeline to serve the area. The Ft. Steele line is poor condition and maintenance is becoming extremely costly. The report recommended complete replacement of the line. Depending upon the option chosen and the eventual use of the water, replacement will cost between $6,000,000 and $12,000,000. The City of Rawlins has requested a Level II study to evaluate possible improvements to their Sage Creek spring collector system, the Fort Steele pipeline, and the water treatment plant. Funding options will also be assessed.

Sinclair has not expressed any interest in pursuing a Level III project in over a year.

RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends that the project be retained at Level II-Hold status.