Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
 Mission Statement
 Directory
 Calendar
 Commission Agendas & Minutes
 Consultant Selection
 Items Open for Public Comment
 Newsletter
 Operating Criteria
 Project Application Information
 Send Us Your Comments

Planning Program
 Dam and Reservoir Planning
 Groundwater Grant Projects
 Instream Flow Filings
 Current Planning Projects
 River Basin Planning
 Weather Modification Study
 Probable Maximum Precipitation
 Water Research Projects

Construction Program
 Current Construction Projects
 Small Water Projects

Agency Publications
 Project Reports
 Water/Climate Web Atlas
 Irrigation & Water System Surveys
 Legislative Reports
 Water Mgmnt & Conservation Dir
 History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

1999 LEGISLATIVE REPORT
Active Projects

109.PROJECT:Wheatland Irrigation District Laramie River Diversion
LEVEL:III
SPONSOR:Wheatland Irrigation District
LOCATION:Albany and Platte Counties
PROGRAM:Rehabilitation
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level II 8 1995 II $100,000   1996
Level III 45 1997 II $315,000* 2000
*50% grant, 50% loan (4%, 20 years)

PROJECT INFORMATION:
The Wheatland Irrigation District received Level III funding for construction of a headwall, measuring device, and control gates for the headgates from the Laramie River into the tunnel for Bluegrass Creek. A portion of the funding was for facilities and equipment for telemetry communication between the headgate, measuring device, Laramie River Diversion Dam, and the district office in Wheatland. When construction bids for the project were opened, the district eliminated the telemetry communication from the project in order to have the structural work completed. Construction of the headwall, measuring device, and control gates will be complete prior to the 1999 irrigation season.

The district has requested additional funding to finance the telemetry equipment and facilities that were eliminated from the project. This component is important to facilitate use of the work completed under this project as well as operation of Sand Lake and other facilities in the Wheatland Irrigation District water delivery system. It is anticipated that $141,500 in additional funds will allow installation of the telemetry equipment and facilities. Construction will likely be completed prior to the irrigation season in 2000.

RECOMMENDED LEGISLATIVE ACTION:
The Commission recommends additional funding in the amount of $141,500 in Level III funding to finance installation of telemetry equipment and facilities. The additional funding would be $70,750 (50%) in grant funds, and $70,750 (50%) in loan funds amortized at 6% interest over 25 years.