Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
 Mission Statement
 Directory
 Calendar
 Commission Agendas & Minutes
 Consultant Selection
 Items Open for Public Comment
 Newsletter
 Operating Criteria
 Project Application Information
 Send Us Your Comments

Planning Program
 Dam and Reservoir Planning
 Groundwater Grant Projects
 Instream Flow Filings
 Current Planning Projects
 River Basin Planning
 Weather Modification Study
 Probable Maximum Precipitation
 Water Research Projects

Construction Program
 Current Construction Projects
 Small Water Projects

Agency Publications
 Project Reports
 Water/Climate Web Atlas
 Irrigation & Water System Surveys
 Legislative Reports
 Water Mgmnt & Conservation Dir
 History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

1999 LEGISLATIVE REPORT
Active Projects

 59. PROJECT:Laramie Transmission Pipeline and Pioneer Canal Diversion
LEVEL:III
SPONSOR:City of Laramie
LOCATION:Albany County
PROGRAM:Rehabilitation
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level III 38 1998 II $4,945,000 2002

PROJECT INFORMATION:
During the 1996-1997 Level III rehabilitation program it was discovered that the severity of the corrosion 36" diameter transmission pipeline was not as extensive as was anticipated, therefore, this pipeline will not need to be replaced. However, the corrosion of the 24" transmission pipeline was discovered to be worse than what was documented in the 1995 Level II study. This pipeline will now need to be replaced. This project is currently under design with the start of construction anticipated in the spring of 1999 and completion for the fall of 2000.

The second component of this project is to rehabilitate the Laramie River Pioneer Canal Diversion structure to accommodate winter flows. Recent growth and population projects require the city to operate its water treatment plant on a year round basis. Presently winter flows to the treatment plant are measured by installing a temporary flume which is plagued by icing conditions. This project will provide a permanent solution to diverting and measuring the flows which will improve the winter time operation. This part of the project is under construction and, barring unforeseen obstacles will be complete in February, 1999.

RECOMMENDED LEGISLATIVE ACTION:
No legislative action required.