Agency Information
Mission Statement
Directory
Calendar
Commission Agendas & Minutes
Consultant Selection
Items Open for Public Comment
Newsletter
Operating Criteria
Project Application Information
Send Us Your Comments
Planning Program
Dam and Reservoir Planning
Groundwater Grant Projects
Instream Flow Filings
Current Planning Projects
River Basin Planning
Weather Modification Study
Probable Maximum Precipitation
Water Research Projects
Construction Program
Current Construction Projects
Small Water Projects
Agency Publications
Project Reports
Water/Climate Web Atlas
Irrigation & Water System Surveys
Legislative Reports
Water Mgmnt & Conservation Dir
History of Wyoming Water Law
WWDC Home Page
Water Plan Home Page
WRDS Home Page
|
2000 LEGISLATIVE REPORT
Active Projects
01. | PROJECT: | Afton Water Supply | | | | | |
| LEVEL: | III |
| SPONSOR: | Town of Afton |
| LOCATION: | Lincoln County |
| PROGRAM: | Rehabilitation |
| |
| EXISTING LEGISLATION: |
|
Purpose |
Chapter |
Session |
Account |
Appropriation |
Due Date |
|
|
Level II |
81 |
1999 |
II |
$75,000 |
2000 |
|
PROJECT INFORMATION:
The Town of Afton wishes to pursue construction of the Periodic Springs
pipeline. The construction effort will consist of wall rock, rubble,
boulder removal and importation of bedding material and concrete to set
a pipe bed, then installation of approximately 1000 feet of pipeline from
the spring outlet down (approx. 170 foot elevation drop) to the existing
97,000 gallon storage tank. The existing pipeline is quite vulnerable,
i.e., subject to rockfall, therefore it is critical to the town's water
supply that the pipeline be replaced and securely re-routed.
RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends the project be incorporated in the Rehabilitation
Program at Level III with an appropriation of $450,000. The financing
plan includes a 50% grant, $225,000 and a 50% loan, $225,000 at 7.25%
interest for 30 years.
|