Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
 Mission Statement
 Directory
 Calendar
 Commission Agendas & Minutes
 Consultant Selection
 Items Open for Public Comment
 Newsletter
 Operating Criteria
 Project Application Information
 Send Us Your Comments

Planning Program
 Dam and Reservoir Planning
 Groundwater Grant Projects
 Instream Flow Filings
 Current Planning Projects
 River Basin Planning
 Weather Modification Study
 Probable Maximum Precipitation
 Water Research Projects

Construction Program
 Current Construction Projects
 Small Water Projects

Agency Publications
 Project Reports
 Water/Climate Web Atlas
 Irrigation & Water System Surveys
 Legislative Reports
 Water Mgmnt & Conservation Dir
 History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

2000 LEGISLATIVE REPORT
Active Projects

 99. PROJECT:Shoshone Rehabilitation
LEVEL:III
SPONSOR:Shoshone Joint Powers Board
LOCATION:Park/Big Horn County
PROGRAM:Rehabilitation
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level III 28 1992 II $7,500,000* 1997
Level III 45 1997     2000
*50% grant

PROJECT INFORMATION:
The Shoshone Joint Powers Board requested assistance from the WWDC for a comprehensive rehabilitation project. The Joint Powers Board is made up of the Heart Mountain, Shoshone, Willwood, and Deaver Irrigation Districts which serve approximately 93,000 acres.

The Bureau, in cooperation with the board and the WWDC, conducted a rehabilitation study of the district's facilities in 1991, and identified a number of major canals and structures in need of repair or replacement. Many of the existing facilities are 80 years old. The estimated total project cost is $15,000,000. Fifty percent of the funds are being provided by the WWDC. The remaining funds are being secured, as a zero interest loan to the board, through the Bureau of Reclamation's Rehabilitation and Betterment Program.

In 1992, the project agreement was completed and executed and the funding agreement with the Bureau of Reclamation was finalized. In addition, the sponsor worked to develop the project work schedule, as well as mitigation plans. In 1993, approximately 21,000 feet of reinforced concrete pipe was manufactured. In addition, 15,000 feet of pipeline was designed, approved and installed, including a large diameter siphon. In 1994, approximately 35,000 feet of reinforced concrete pipe and a large drop structure was installed; and grouting of the Cedar Mountain Tunnel commenced. In 1995, 10,000 feet of pipe and two large drop structures were installed and work continued on the Cedar Mountain Tunnel. In 1996, 25,000 feet of pipe and two large drop structures were installed and grouting continued on the Cedar Mountain Tunnel. In 1997, 33,000 feet of pipe and three large drop structures were installed and grouting continued on the Cedar Mountain Tunnel. In 1998, installation of 82,000 feet of pipe, one large drop structure, and work on the flumed section of the Cedar Mountain Tunnel were completed. In 1999, 103,000 feet of pipe and various canal structures were installed. The Shoshone River Siphon was re-coated and a portion of the Heart Mountain Canal was concrete lined. The Willwood Canal Gates on the Willwood Dam were also rehabilitated. In 2000, the Buck Springs Creek Siphon will be rehabilitated to complete the project.

RECOMMENDED LEGISLATIVE ACTION:
No legislative action is required.

   Citizen    Government    Business    Visitor   Privacy Policy