Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
 Mission Statement
 Directory
 Calendar
 Commission Agendas & Minutes
 Consultant Selection
 Items Open for Public Comment
 Newsletter
 Operating Criteria
 Project Application Information
 Send Us Your Comments

Planning Program
 Dam and Reservoir Planning
 Groundwater Grant Projects
 Instream Flow Filings
 Current Planning Projects
 River Basin Planning
 Weather Modification Study
 Probable Maximum Precipitation
 Water Research Projects

Construction Program
 Current Construction Projects
 Small Water Projects

Agency Publications
 Project Reports
 Water/Climate Web Atlas
 Irrigation & Water System Surveys
 Legislative Reports
 Water Mgmnt & Conservation Dir
 History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

2000 LEGISLATIVE REPORT
Active Projects

101.PROJECT:Smiths Fork Dam
LEVEL:II-Hold
SPONSOR:State of Wyoming
LOCATION:Lincoln County
PROGRAM:New Development
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level II 10 1994 I Hold   1996
Level II 15 1996 I Hold   1998
Level II 82 1998 I Hold* 2000
*A block appropriation of $15,000 was made for all hold projects.

PROJECT INFORMATION:
In 1984, the States of Wyoming, Utah and Idaho joined forces to evaluate the potential of a project on the Smiths Fork of the Bear River which would serve to provide benefits to all three states. Since that time, the project has evolved to a 50,000 acre-foot reservoir which would cost approximately $35,000,000. The project would provide water supply, hydropower, water quality, flood control and recreation benefits. In 1986, the State of Utah prepared an economic feasibility report which concluded that the project was economically feasible if all three states participated in the costs and the benefits.

Relative to Wyoming, the project could provide flood control, recreation, hydropower, and supplemental irrigation water supply benefits. Presently, the tri-state Smiths Fork project appears to be the most economical means to develop the Cokeville and Cokeville Development Association's storage allocation of 14,520 acre-feet. Therefore, the WWDC has included the Smiths Fork among its candidates for state projects to be pursued as financial resources are available. However, a primary consideration will be the ability of the states of Utah and Idaho to obtain their share of required project funding.

In 1988, the U.S. Corps of Engineers (COE) prepared a development plan for the entire Bear River. The report was completed in 1989. Several options were identified. The report verified that a dam on the Smiths Fork would provide considerable flood control, storage and water quality benefits. However, the economic assessment concluded that the project had an unfavorable benefit-cost ratio and, therefore, would not be eligible for federal funding under existing criteria. The project is presently on hold status in the New Development Program. There is local and increasing downstream interest in the project.

RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends that the project be retained at Level II-Hold status.