Agency Information
Mission Statement
Directory
Calendar
Commission Agendas & Minutes
Consultant Selection
Items Open for Public Comment
Newsletter
Operating Criteria
Project Application Information
Send Us Your Comments
Planning Program
Dam and Reservoir Planning
Groundwater Grant Projects
Instream Flow Filings
Current Planning Projects
River Basin Planning
Weather Modification Study
Probable Maximum Precipitation
Water Research Projects
Construction Program
Current Construction Projects
Small Water Projects
Agency Publications
Project Reports
Water/Climate Web Atlas
Irrigation & Water System Surveys
Legislative Reports
Water Mgmnt & Conservation Dir
History of Wyoming Water Law
WWDC Home Page
Water Plan Home Page
WRDS Home Page
|
2000 LEGISLATIVE REPORT
Active Projects
114. | PROJECT: | Wheatland Irrigation District Laramie River Diversion | | | | | |
| LEVEL: | III |
| SPONSOR: | Wheatland Irrigation District |
| LOCATION: | Albany and Platte Counties |
| PROGRAM: | Rehabilitation |
| |
| EXISTING LEGISLATION: |
|
Purpose |
Chapter |
Session |
Account |
Appropriation |
Due Date |
|
|
Level II |
8 |
1995 |
II |
$100,000 |
1996 |
|
|
Level III |
45 |
1997 |
II |
$315,000* |
2000 |
|
|
Level III |
16 |
1999 |
II |
$141,500* |
2000 |
|
| *50% grant, 50% loan (4%, 20 years) |
PROJECT INFORMATION:
The Wheatland Irrigation District received Level III funding for
construction of a headwall, measuring device, and control gates for the
headgates from the Laramie River into the tunnel for Bluegrass Creek.
A portion of the funding was for facilities and equipment for telemetry
communication between the headgate, measuring device, Laramie River
Diversion Dam, and the district office in Wheatland. When construction
bids for the project were opened, the district eliminated the telemetry
communication from the project in order to have the structural work
completed. Construction of the headwall, measuring device, and control
gates was completed prior to the 1999 irrigation season. The sponsor is
pursuing district court approval for the increased project budget to
proceed with installation of the telemetry system.
RECOMMENDED LEGISLATIVE ACTION:
No legislative action is required.
|