Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
 Mission Statement
 Directory
 Calendar
 Commission Agendas & Minutes
 Consultant Selection
 Items Open for Public Comment
 Newsletter
 Operating Criteria
 Project Application Information
 Send Us Your Comments

Planning Program
 Dam and Reservoir Planning
 Groundwater Grant Projects
 Instream Flow Filings
 Current Planning Projects
 River Basin Planning
 Weather Modification Study
 Probable Maximum Precipitation
 Water Research Projects

Construction Program
 Current Construction Projects
 Small Water Projects

Agency Publications
 Project Reports
 Water/Climate Web Atlas
 Irrigation & Water System Surveys
 Legislative Reports
 Water Mgmnt & Conservation Dir
 History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

2001 LEGISLATIVE REPORT
Active Projects

118.PROJECT:Wamsutter Water Supply
LEVEL:Level II
SPONSOR:Town of Wamsutter
LOCATION:Sweetwater County
PROGRAM:Rehabilitation
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level II 46 1997 I $105,000 1998

PROJECT INFORMATION:
This project includes refinancing of an existing State Land and Investment Board emergency loan that funded the replacement of an old three inch diameter transmission line, funded the construction of a transmission line to connect an existing but unused well to the town's system and other appurtenant facilities. The connection of the well previously drilled under a WWDC groundwater grant will replace the town's old well system drilled around the early 1900s.

The Level II study identified a total of about 2.1 million dollars of needed improvements. The town has been planning to phase the construction of the identified components. This project is phase one and had to be accelerated to be able to utilize a grant from industry to help pay for improvements.

RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends that the project be included in the program at Level III status in the Rehabilitation Program with an appropriation of $140,000. The total project budget is estimated to be $280,000. The financing plan is a 50% grant, $140,000, and 50% is to be secured by the sponsor through other sources.