Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
 Mission Statement
 Directory
 Calendar
 Commission Agendas & Minutes
 Consultant Selection
 Items Open for Public Comment
 Newsletter
 Operating Criteria
 Project Application Information
 Send Us Your Comments

Planning Program
 Dam and Reservoir Planning
 Groundwater Grant Projects
 Instream Flow Filings
 Current Planning Projects
 River Basin Planning
 Weather Modification Study
 Probable Maximum Precipitation
 Water Research Projects

Construction Program
 Current Construction Projects
 Small Water Projects

Agency Publications
 Project Reports
 Water/Climate Web Atlas
 Irrigation & Water System Surveys
 Legislative Reports
 Water Mgmnt & Conservation Dir
 History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

2002 LEGISLATIVE REPORT
Active Projects

 44. PROJECT:Glenrock Groundwater Supply
LEVEL:III
SPONSOR:Town of Glenrock
LOCATION:Converse County
PROGRAM:New Development
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level II 82 1999 I $75,000 2000
Level II 81 1999 I $300,000 2000
Level III 96 2000 I $1,650,000 2004

PROJECT DESCRIPTION:
The town of Glenrock has purchased the supply test well No. 5 drilled under a Level II study conducted in 1999. Construction tasks include installation of a pump, pump house, 10,220 feet of 14 inch transmission line, 11,200 feet of powerline, improvements along the transmission line (air/vacuum valves, blowoffs, roadbase, ravine crossings, etc.), installation of a PRV building, and SCADA equipment.

Civil Engineering Professionals Incorporated of Casper has been retained to design the improvements. Additional groundwater monitoring has been undertaken to insure impacts from the new well are identified and mitigated.

A construction contract for this work was awarded to 71 Construction of Casper in November 2001. However, only three of the four bid schedules can be completed given the available funding. The City has applied for additional funding of $ 175,000.

RECOMMENDED LEGISLATIVE ACTION:
It is recommended that the additional funding of $175,000 be approved to allow completion of the entire project.