PROJECT INFORMATION:
The Town of Alpine would like to move forward with the design to both the improvements to
Little Jenny Lake Spring area and the raw water irrigation system that was recommended in the
Level II study completed in October 2001.
The applicant requests funding to finance the first phase of a two-phase construction project.
Phase 1 also includes engineering design and specifications for the second phase. Phase I also
addressed permitting and mitigation work, legal fees and rights-of-way issues. Phase 2 would
include constructing improvements to the spring area and installation of the irrigation system.
Phase II of the project was approved by 2002 Legislature. The field work is complete and
negotiations with the U.S. Forest Service and WYDOT are underway. This phase should be
complete in early 2003.
RECOMMENDED LEGISLATIVE ACTION:
No legislative action is required.