Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
 Mission Statement
 Directory
 Calendar
 Commission Agendas & Minutes
 Consultant Selection
 Items Open for Public Comment
 Newsletter
 Operating Criteria
 Project Application Information
 Send Us Your Comments

Planning Program
 Dam and Reservoir Planning
 Groundwater Grant Projects
 Instream Flow Filings
 Current Planning Projects
 River Basin Planning
 Weather Modification Study
 Probable Maximum Precipitation
 Water Research Projects

Construction Program
 Current Construction Projects
 Small Water Projects

Agency Publications
 Project Reports
 Water/Climate Web Atlas
 Irrigation & Water System Surveys
 Legislative Reports
 Water Mgmnt & Conservation Dir
 History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

2003 LEGISLATIVE REPORT
Active Projects

 28. PROJECT:Chugwater Water Supply
LEVEL:III
SPONSOR:Town of Chugwater
LOCATION:Platte County
PROGRAM:New Development
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level I 15 1996 I $75,000     1998
Level II 46 1997 I $100,000     1998
Level III 45 1997 II $103,500*   2000
Level III 16 1999 I $967,800** 2003
*50% grant
**60% grant

PROJECT INFORMATION:
Under the 1997 Level III construction appropriation the pipeline from the in-town wells to the storage tank was replaced with larger pipe. Under the 1999 Level III construction appropriation one in-town well has been replaced and the other rehabilitated. A contract has been awarded to build a new water storage tank west of town and install connecting piping between the new tank and the distribution system. The town has purchased property west of town subsequent to finding a promising groundwater supply there. With the passage of time, inflation, and more distant wellfield location will require that both additional time and additional funding of $400,000 be approved by the legislature in order for the project to be completed. The project is being funded by WWDC and RUS on a 60/40 split, with WWDC providing 60% of the funding as grant funds. The balance of financing will be provided by RUS and/or other sources. This request is for an additional $240,000 in water development account grant funds and an extension of the reversion date to July 1, 2007 will allow for the completion of the project. With the additional time and funding this project will provide the town with a new water source away from the potential hazards of the in-town wellfield area.

RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends the reversion date for project funding be amended to be July 1, 2007. WWDC recommends the level III appropriation from the new development account for project funding be amended to be $1,207,800. The financing plan is a 60% grant, $1,207,800. The balance of financing for the $2,013,000 project budget will be provided by RUS and /or other sources.