Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
 Mission Statement
 Directory
 Calendar
 Commission Agendas & Minutes
 Consultant Selection
 Items Open for Public Comment
 Newsletter
 Operating Criteria
 Project Application Information
 Send Us Your Comments

Planning Program
 Dam and Reservoir Planning
 Groundwater Grant Projects
 Instream Flow Filings
 Current Planning Projects
 River Basin Planning
 Weather Modification Study
 Probable Maximum Precipitation
 Water Research Projects

Construction Program
 Current Construction Projects
 Small Water Projects

Agency Publications
 Project Reports
 Water/Climate Web Atlas
 Irrigation & Water System Surveys
 Legislative Reports
 Water Mgmnt & Conservation Dir
 History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

2003 LEGISLATIVE REPORT
Active Projects

 82. PROJECT:Moorcroft Well
LEVEL:II
SPONSOR:Town of Moorcroft
LOCATION:Crook County
PROGRAM:New Development
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level I 38 1992 I $35,000 1992
Level II 74 1994 I $225,000 1994
Level III 28 1994 I $930,000 1997
Level II 36 2000 I $355,000 2002
Level II 86 2001 I $145,000 2002

PROJECT INFORMATION:
In 1992, a Level I study conducted for the town of Moorcroft recommended construction of a new storage tank and connection piping collection system. The study also recommended that both a Lance/Fox Hills Formation well and a Madison Formation well be developed. In 1994, after the conclusion of a Level II study, the town of Moorcroft constructed the new storage tank, system piping, and drilled a new Lance/Fox Hills test well. The Madison test well has also recently been drilled.

The test well was completed in October of 2001 to a total depth of 3,750 feet into the Madison Limestone aquifer. The well was constant-rate pump tested at 602 gpm over a seven-day period with a resultant drawdown of 76 feet. This rate is over 5 times the present capacity of their existing wells. The water quality is within primary drinking water standards but is extremely hard (605 mg/L as CaCO3) and therefore some treatment will be required for specific uses. The Town has applied for 2003 funding from WWDC and USDA-RUS. The test wells will be connected to the Town's distribution system.

Estimated Level III Costs

Final Designs & Specifications$ 265,817.20
Permitting & Mitigation11,150.00
Legal Fees4,000.00
Access & ROW82,210.00
Project Components$ 2,658,172.00
Engineering265,817.20
Construction Cost (Subtotal)$ 2,923,989.20
Contingency (15%)438,598.38
Construction Cost Total (Subtotal)$ 3,362,587.58
  
Project Total Construction Cost$ 3,725,764.78
Project Total Cost (Rounded)$ 3,750,000

Purchase Price of Moorcroft Madison #1 Well - $129,031.40

RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends the project be incorporated into the New Development Program at Level III with an appropriation of $2,250,000 (60% Grant).