PROJECT INFORMATION:
The Town of Pinedale would like a study undertaken to determine the feasibility and cost of
placing hydropower generators in their water system between Fremont Lake and the town. They
have two areas that could provide hydropower. The first area is the Pine Creek Fremont Lake
outflow. This area had a power plant years ago. The second area is the supply line from the lake
to town.
This study will also include a study or the transmission requirements to get the generated power
to a power user.
This is a two-year study with the final report due May 2003.
RECOMMENDED LEGISLATIVE ACTION:
No legislative action is required.