Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
 Mission Statement
 Directory
 Calendar
 Commission Agendas & Minutes
 Consultant Selection
 Items Open for Public Comment
 Newsletter
 Operating Criteria
 Project Application Information
 Send Us Your Comments

Planning Program
 Dam and Reservoir Planning
 Groundwater Grant Projects
 Instream Flow Filings
 Current Planning Projects
 River Basin Planning
 Weather Modification Study
 Probable Maximum Precipitation
 Water Research Projects

Construction Program
 Current Construction Projects
 Small Water Projects

Agency Publications
 Project Reports
 Water/Climate Web Atlas
 Irrigation & Water System Surveys
 Legislative Reports
 Water Mgmnt & Conservation Dir
 History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

2003 LEGISLATIVE REPORT
Active Projects

 96. PROJECT:Pine Haven Madison Test Well
LEVEL:II
SPONSOR:Town of Pine Haven
LOCATION:Crook County
PROGRAM:New Development
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level I 36 2000 I $35,000 2001
Level III 2 2001 I $235,000 2004
Level II 7 2002 I $575,000 2004

PROJECT INFORMATION:
The "Town of Pine Haven Water System Master Plan," completed by Stetson Engineering in 2000, recommended that a second source supply well be developed to meet increased demands associated with growth and development and to provide system redundancy. The town currently has only one source of supply, the Keyhole No. 1 Well. If this well should fail, the community would be out of water as soon as the storage tank emptied. To increase the reliability of service to the water system, it would be advantageous to have a second supply well.

A successful Madison Formation Aquifer test well was drilled and tested in August/September of 2002. The town is requesting Level III funding for 2003 to tie the new well into the water supply system.

Estimated Level III Costs
Final Designs & Specifications$ 19,481.00
Permitting & Mitigation5,000.00
Legal Fees5,000.00
Access & ROW5,000.00
Project Components154,000.00
Engineering5,400.00
Construction Cost (Subtotal)$ 169,400.00
Contingency (15%)25,410.00
Construction Cost Total (Subtotal)$ 194,810.00
Project Total Construction Cost$ 229,291.00
Rounded Total Cost$ 230,000

Purchase Price of Pine Haven Madison #2 Well - $144,847.45 (WWDC Loan)

RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends the project be incorporated into the New Development Program at Level III with an appropriation of $115,000 (50% Grant).