Agency Information
Mission Statement
Directory
Calendar
Commission Agendas & Minutes
Consultant Selection
Items Open for Public Comment
Newsletter
Operating Criteria
Project Application Information
Send Us Your Comments
Planning Program
Dam and Reservoir Planning
Groundwater Grant Projects
Instream Flow Filings
Current Planning Projects
River Basin Planning
Weather Modification Study
Probable Maximum Precipitation
Water Research Projects
Construction Program
Current Construction Projects
Small Water Projects
Agency Publications
Project Reports
Water/Climate Web Atlas
Irrigation & Water System Surveys
Legislative Reports
Water Mgmnt & Conservation Dir
History of Wyoming Water Law
WWDC Home Page
Water Plan Home Page
WRDS Home Page
|
2003 LEGISLATIVE REPORT
Active Projects
108. | PROJECT: | Riverton Valley Rehabilitation #2, Phase II/Riverton Valley | | | | | |
| | Underflow Project | | | | | |
| LEVEL: | II |
| SPONSOR: | Riverton Valley Irrigation District |
| LOCATION: | Fremont County |
| PROGRAM: | Rehabilitation |
| |
| EXISTING LEGISLATION: |
|
Purpose |
Chapter |
Session |
Account |
Appropriation |
Due Date |
|
|
Level II |
7 |
2002 |
II |
$40,000 |
2004 |
|
PROJECT INFORMATION:
The district has approached the Commission for Level III construction funds to rehabilitate four
underflow structures that were evaluated during a recently completed Level II Study. These
1930's vintage structures handle upstream return flow and flood flow and protect the canal from
flood related erosion. The four crossings are in various states of disrepair, with Madden Draw
being in the worst condition, as the underflow structure has already partially failed (caved in).
Additionally, the corrugated metal pipe utilized at these crossings is not sized correctly to handle
extreme events. Rehabilitation of these crossings would provide protection to the canal during
flood flows and ultimately improve the ability and reliability of the system to deliver water to the
users.
-
The design and construction costs are displayed below:
Design | $ 11,920 |
Permitting and Mitigation | $ 2,500 |
Legal Fees | $ 2,384 |
Acquisition of Access and Right-of-Way | $ 2,384 |
Project Components | $ 94,225 |
Engineering (10%) | $ 9,423 |
Construction Cost (Subtotal) | $ 103,648 |
Contingency (15%) | $ 15,547 |
Construction Cost Total (Subtotal) | $ 119,195 |
Project Total Construction Cost | $ 138,383 |
Rounded | $ 140,000 |
RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends the project be incorporated in the Rehabilitation Program and advanced
to Level III construction with an appropriation of $140,000. The financing plan is a 50% grant,
$70,000 and a 50% loan, $70,000 for twenty-five years at 6.00% interest.
|