Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
 Mission Statement
 Directory
 Calendar
 Commission Agendas & Minutes
 Consultant Selection
 Items Open for Public Comment
 Newsletter
 Operating Criteria
 Project Application Information
 Send Us Your Comments

Planning Program
 Dam and Reservoir Planning
 Groundwater Grant Projects
 Instream Flow Filings
 Current Planning Projects
 River Basin Planning
 Weather Modification Study
 Probable Maximum Precipitation
 Water Research Projects

Construction Program
 Current Construction Projects
 Small Water Projects

Agency Publications
 Project Reports
 Water/Climate Web Atlas
 Irrigation & Water System Surveys
 Legislative Reports
 Water Mgmnt & Conservation Dir
 History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

2003 LEGISLATIVE REPORT
Active Projects

135.PROJECT:Washakie Rural Water Supply
LEVEL:III
SPONSOR:Washakie Rural Improvement District
LOCATION:Washakie County
PROGRAM:New Development
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level I 10 1994 I $100,000   1996
Level II 15 1996 I Hold* 1998
Level II 82 1998 I $100,000   2000
Level III 16 1999 I $5,220,000* 2004
Level III 2 2001 I $240,000   2004
*60% grant, balance of project cost from other sources.

PROJECT INFORMATION:
The project consists of a rural water system extending from the Hot Springs county line on the south, to the Big Horn county line on the north, and encompasses most of the private lands along both sides of the Big Horn River. The new system will obtain its water from the city of Worland, who has an ample supply from two flowing Madison-Bighorn formation wells. The system will operate entirely by gravity flow.

The district's members currently utilize individual wells, which generally exceed EPA secondary regulations for TDS and Sulfates. Some local wells are also high in sodium, selenium, and nitrate. It is estimated that up to 70% of the district's members haul water or utilize bottled water for domestic use. The first phase construction will begin in 2001.

The McNutt Improvement and Service District project has been combined with this project.

This project is being constructed in several phases so smaller local contractors can compete. Construction of Phase I has begun and will be completed in 2002. Phase II plans are nearly complete. Bids for Phase II will be solicited early in 2002. Additional phases will be constructed as plans are developed. At least two additional phases are expected.

The Washakie Rural Improvement District's project was originally funded in 1999. Due to difficulties with: obtaining a water purchase agreement with the City of Worland; preparation of an acceptable design; obtaining easements; and assessing the impact of the future Big Horn Regional project, construction of the first phase of this project was not started until May 2001. Conflicts with the contractor on Phase I resulted in several claims being filed by the contractor.

A negotiated settlement resulted in an unanticipated contract increase. Upon placing the Phase I project into service, problems with the design became evident. Subsequently, the engineering consultant's contract was terminated. A new consultant was selected through a competitive qualification based selection process.

Several factors have contributed to the revised project cost projections, they are: (1) The construction cost estimates presented in the Level II studies were developed in 1998 dollars and the delays noted prolonged the completion of phases of the project to the extent that inflation costs compounded; (2) The project engineering costs presented in the Level II studies were low; (3) Material costs escalated after the completion of the Level II studies due to increased oil prices; (4) Time delays caused by an inability to consummate a water purchase agreement with the City of Worland; (5) Difficulties with obtaining easements from property owners and the Wyoming Department of Transportation resulted in changes to several proposed pipeline alignments; (6) Difficulties with the Phase I contractor; (7) The addition of district staff necessary to manage the project at the local level; (8) problems with the Phase I design; and, (9) Replacement of the original consultant.

RECOMMENDED LEGISLATIVE ACTION:
This WWDC recommendation to increase the project appropriation with an additional grant, in the amount of $3,000,000. The Rural Utilities Service will be providing an additional loan in the amount of $500,000.00 and an additional grant in the amount of $1,000,000.00. Also, the District is requesting a Mineral Royalties Grant in the amount of $324,000.00. With these additional funds, the District will be able to complete the construction project.