PROJECT INFORMATION:
This project would provide funding for the design and construction of a new well, new storage,
and pipeline to connect the improvements to the town of Wheatland's system. The improvements
would provide additional supply to the southwest portion of town. This area includes a new
school that cannot be used until sufficient water supply in the area is available.
The project has been included at Level III status in the Rehabilitation Program with an
appropriation of $222,000. The total project budget is estimated to be $854,000. The financing
plan is a 26% grant, $222,000, and 74% of the project budget being secured by the sponsor
through other sources.
Plans have been prepared and construction of the water storage tank is complete. Plans have been
prepared for the pressure reducing vaults and construction is complete.
RECOMMENDED LEGISLATIVE ACTION:
No legislative action is required.