Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
green drop bullet Mission Statement
green drop bullet Directory
green drop bullet Calendar
green drop bullet Commission Agendas & Minutes
green drop bullet Consultant Selection
green drop bullet Items Open for Public Comment
green drop bullet Newsletter
green drop bullet Operating Criteria
green drop bullet Project Application Information
green drop bullet Send Us Your Comments

Planning Program
green drop bullet Dam and Reservoir Planning
green drop bullet Groundwater Grant Projects
green drop bullet Instream Flow Filings
green drop bullet Current Planning Projects
green drop bullet River Basin Planning
green drop bullet Weather Modification Study
green drop bullet Probable Maximum Precipitation
green drop bullet Water Research Projects

Construction Program
green drop bullet Current Construction Projects
green drop bullet Small Water Projects

Agency Publications
green drop bullet Project Reports
green drop bullet Water/Climate Web Atlas
green drop bullet Irrigation & Water System Surveys
green drop bullet Legislative Reports
green drop bullet Water Mgmnt & Conservation Dir
green drop bullet History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

1996 LEGISLATIVE REPORT
Project Reports

 55. PROJECT:Natrona County Regional Rehabilitation
LEVEL:III
SPONSOR:Natrona County Regional Water System Joint Powers Board
LOCATION:Natrona County
PROGRAM:New Development
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level III-I 206 1995 I $1,500,000* 1999
*50% grant, 50% loan (4%, 30 years)

PROJECT INFORMATION:
The aggregate population of the entities served by the Natrona County Regional Water System Joint Powers Board is approximately 60,000 residents. The Level II feasibility study of the Natrona County Regional Water Supply Project identified $60,000,000 of needed improvements, of which $37,000,000 would be eligible for WWDC assistance, and identified a phased approach for completing the project. Some infrastructure improvements should be completed by 1997 to facilitate operation of the regional system.

The Level II feasibility study of the Natrona County Regional Water Supply Project recommended that the Fort Caspar and Dempsey Acres Well Fields be rehabilitated. The estimated cost for this component of the project is $4,814,000. The project will be completed in three phases: drilling, final design, and construction. The well fields are a primary water supply for the regional system. The existing wells are old and production has dropped. The project would serve to increase the well production to its permitted amount. In addition, several water storage tanks will be operated by the Joint Powers Board. Telemetry modifications to the tanks and some rehabilitation is required to extend their usable life. The estimated cost for the improvements to the storage tanks is $586,000. The funding for these project components would be provided from the Rehabilitation account. Because of limited funds available, the WWDC recommended that this project be phased.

RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends that the Level III appropriation be increased from $1,500,000 to $5,300,000 or $3,800,000. The recommended financing plan remains a 50% grant and a 50% loan with an interest rate of 4% and a term of 30 years.