Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
green drop bullet Mission Statement
green drop bullet Directory
green drop bullet Calendar
green drop bullet Commission Agendas & Minutes
green drop bullet Consultant Selection
green drop bullet Items Open for Public Comment
green drop bullet Newsletter
green drop bullet Operating Criteria
green drop bullet Project Application Information
green drop bullet Send Us Your Comments

Planning Program
green drop bullet Dam and Reservoir Planning
green drop bullet Groundwater Grant Projects
green drop bullet Instream Flow Filings
green drop bullet Current Planning Projects
green drop bullet River Basin Planning
green drop bullet Weather Modification Study
green drop bullet Probable Maximum Precipitation
green drop bullet Water Research Projects

Construction Program
green drop bullet Current Construction Projects
green drop bullet Small Water Projects

Agency Publications
green drop bullet Project Reports
green drop bullet Water/Climate Web Atlas
green drop bullet Irrigation & Water System Surveys
green drop bullet Legislative Reports
green drop bullet Water Mgmnt & Conservation Dir
green drop bullet History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

1996 LEGISLATIVE REPORT
Project Reports

 68. PROJECT:Rolling Hills Water Supply
LEVEL:II
SPONSOR:Town of Rolling Hills
LOCATION:Converse County
PROGRAM:New Development
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level I 8 1995 I $200,000 1996

PROJECT INFORMATION:
The Town of Rolling Hills received assistance from the Water Development Commission in the past to construct a Lance Formation well and improvements to the town's storage and transmission system. While the WWDC well is in good condition and remains a major water source, the two older wells apparently were improperly constructed and developed. The wells are also located too close together and cannot be pumped at maximum capacity at the same time.

The Level II project included construction of an additional well, evaluation of the existing water system, and preparation of conceptual designs and cost estimates for needed improvements.

The project includes the new well that was completed during Level II ($80,000), the pumping system, building, controls, and appurtenances ($115,000), the pipeline and appurtenances necessary to connect the new well to the existing transmission system ($11,500), and a chlorination system ($3,500).

RECOMMENDED LEGISLATIVE ACTION:
The Commission recommends that the project be advanced to Level III status in the New Development Program with a budget of $200,000. The financing plan includes a 67% grant and a 33% loan (4%, 20 years). The sponsor will be required to reimburse the WWDC for 33% of the Level II well construction cost ($26,400, 4%, 20 years).