Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
green drop bullet Mission Statement
green drop bullet Directory
green drop bullet Calendar
green drop bullet Commission Agendas & Minutes
green drop bullet Consultant Selection
green drop bullet Items Open for Public Comment
green drop bullet Newsletter
green drop bullet Operating Criteria
green drop bullet Project Application Information
green drop bullet Send Us Your Comments

Planning Program
green drop bullet Dam and Reservoir Planning
green drop bullet Groundwater Grant Projects
green drop bullet Instream Flow Filings
green drop bullet Current Planning Projects
green drop bullet River Basin Planning
green drop bullet Weather Modification Study
green drop bullet Probable Maximum Precipitation
green drop bullet Water Research Projects

Construction Program
green drop bullet Current Construction Projects
green drop bullet Small Water Projects

Agency Publications
green drop bullet Project Reports
green drop bullet Water/Climate Web Atlas
green drop bullet Irrigation & Water System Surveys
green drop bullet Legislative Reports
green drop bullet Water Mgmnt & Conservation Dir
green drop bullet History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

1996 LEGISLATIVE REPORT
Project Reports

 81. PROJECT:Stewart Creek Pipeline
LEVEL:II-Hold
SPONSOR:Stewart Creek Irrigation Company
LOCATION:Lincoln County
PROGRAM:Rehabilitation
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level II 10 1994 I Hold* 1996
*A block appropriation of $29,000 was made for all hold projects.

PROJECT INFORMATION:
The company serves 15 shareholders, and about 1100 irrigated acres. The project has consisted of studying the feasibility of repairs needed on the sponsor's gravity pipeline system. The system was installed in 1961 and is in poor condition. The annual maintenance costs of this system are now exceeding reasonable levels.

The Level II study found that approximately 500 feet of the pipeline needs to be replaced. The rest of the system can be regulated through the repair of existing pressure relief valves and the addition of relief valves to balance the delivery of the limited supply of water available to the system. The company must form an irrigation district if it wishes to pursue Level III funding.

RECOMMENDED LEGISLATIVE ACTION:
No legislative action is required on this project.