Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
green drop bullet Mission Statement
green drop bullet Directory
green drop bullet Calendar
green drop bullet Commission Agendas & Minutes
green drop bullet Consultant Selection
green drop bullet Items Open for Public Comment
green drop bullet Newsletter
green drop bullet Operating Criteria
green drop bullet Project Application Information
green drop bullet Send Us Your Comments

Planning Program
green drop bullet Dam and Reservoir Planning
green drop bullet Groundwater Grant Projects
green drop bullet Instream Flow Filings
green drop bullet Current Planning Projects
green drop bullet River Basin Planning
green drop bullet Weather Modification Study
green drop bullet Probable Maximum Precipitation
green drop bullet Water Research Projects

Construction Program
green drop bullet Current Construction Projects
green drop bullet Small Water Projects

Agency Publications
green drop bullet Project Reports
green drop bullet Water/Climate Web Atlas
green drop bullet Irrigation & Water System Surveys
green drop bullet Legislative Reports
green drop bullet Water Mgmnt & Conservation Dir
green drop bullet History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

1998 LEGISLATIVE REPORT
Project Reports

 37. PROJECT:Gillette Storage & East End Transmission Improvements
LEVEL:New Application
SPONSOR:City of Gillette
LOCATION:Campbell County
PROGRAM:New Development

PROJECT INFORMATION:
The City of Gillette would like to accelerate construction of the recommended Phase III improvements, as identified in the Gillette Area Master Plan. The new storage reservoir will allow the city to meet maximum daily demands and provide sufficient fire flows. This reservoir will provide two days of storage if the 43 mile long Madison pipeline were to be out of service.

Construction of the east end transmission pipeline will complete a major loop in the city's transmission system and will provide needed fire protection to this area of town. This improvement was also identified in the Gillette Area Master Plan.

RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends that the projects be introduced as a Level III new development project. The recommended funding is grant funds in the amount of $2,040,000 which represents 60% of the project costs. The City of Gillette will provide the remaining 40% funding from other sources.