Agency Information
Mission Statement
Directory
Calendar
Commission Agendas & Minutes
Consultant Selection
Items Open for Public Comment
Newsletter
Operating Criteria
Project Application Information
Send Us Your Comments
Planning Program
Dam and Reservoir Planning
Groundwater Grant Projects
Instream Flow Filings
Current Planning Projects
River Basin Planning
Weather Modification Study
Probable Maximum Precipitation
Water Research Projects
Construction Program
Current Construction Projects
Small Water Projects
Agency Publications
Project Reports
Water/Climate Web Atlas
Irrigation & Water System Surveys
Legislative Reports
Water Mgmnt & Conservation Dir
History of Wyoming Water Law
WWDC Home Page
Water Plan Home Page
WRDS Home Page
|
1999 LEGISLATIVE REPORT
Active Projects
08. | PROJECT: | Buffalo Municipal Reservoir | | | | | |
| LEVEL: | III |
| SPONSOR: | City of Buffalo |
| LOCATION: | Johnson County |
| PROGRAM: | New Development |
| |
| EXISTING LEGISLATION: |
|
Purpose |
Chapter |
Session |
Account |
Appropriation |
Due Date |
|
|
Level III |
28 |
1992 |
I |
$10,650,000* |
1999 |
|
|
Level III |
59 |
1996 |
I |
$2,450,000* |
1999 |
|
|
Level III |
45 |
1997 |
I |
$500,000* |
1999 |
|
| *67% grant, 33% loan (4%, 50 years, 5 year deferral) |
PROJECT INFORMATION:
The Buffalo Municipal Reservoir Project involves development of a
municipal supply storage reservoir in the Clear Creek Basin west of
Buffalo. Buffalo's existing water supply is diverted from Clear Creek
about six miles west of the city. After project completion, releases
from the reservoir will supplement Clear Creek flow when the direct flow
cannot fulfill Buffalo's water supply requirements.
The Level II - Phase I report was completed in March, 1989. The report
concluded that the preferred development option included a dam and
reservoir at the Lower Tie Hack site on South Clear Creek, a tributary
of Clear Creek. The recommended reservoir size is 2425 acre feet and
the estimated cost of the dam and reservoir was $10,650,000. In
addition, the report indicated that installation of a $975,000
hydropower generation unit at the downstream end of the city's water
supply pipeline could be economically advantageous. The hydropower unit
is addressed as a separate project, but construction of both components
is required if the total project is to be economically feasible. The
report also noted that the feasibility of the project would depend on
the successful transfer of Buffalo's existing 1933 filing for 1640 acre
feet from Little Sourdough Creek to the dam site. This transfer was
accomplished in 1990.
In 1992, the WWDC and city completed the project agreement, note and
mortgage needed before the city could access project funds. The city
has negotiated the necessary agreements with the Big Horn National
Forest relative to the completion of the environmental impact statement.
The Final Environmental Impact Statement has been published and no
protests have been received. The final design has been completed and
construction bids were opened and reviewed in January, 1996. The Forest
Service special use permit was issued on February 23, 1996, and the U.S.
Army Corps of Engineers 404 permit was issued on March 5, 1996.
Construction commenced in April, 1996, with substantial completion
reached in November, 1997. Although the project is substantially
completed, final completion of the project will be achieved in 1999. A
small campground which will be inundated by the new reservoir will be
replaced by the Forest Service in 1999.
RECOMMENDED LEGISLATIVE ACTION:
No legislative action is required on this project.
|