Agency Information
Mission Statement
Directory
Calendar
Commission Agendas & Minutes
Consultant Selection
Items Open for Public Comment
Newsletter
Operating Criteria
Project Application Information
Send Us Your Comments
Planning Program
Dam and Reservoir Planning
Groundwater Grant Projects
Instream Flow Filings
Current Planning Projects
River Basin Planning
Weather Modification Study
Probable Maximum Precipitation
Water Research Projects
Construction Program
Current Construction Projects
Small Water Projects
Agency Publications
Project Reports
Water/Climate Web Atlas
Irrigation & Water System Surveys
Legislative Reports
Water Mgmnt & Conservation Dir
History of Wyoming Water Law
WWDC Home Page
Water Plan Home Page
WRDS Home Page
|
1999 LEGISLATIVE REPORT
Active Projects
55. | PROJECT: | Lander Intake Facilities | | | | | |
| LEVEL: | II |
| SPONSOR: | City of Lander |
| LOCATION: | Fremont County |
| PROGRAM: | Rehabilitation |
| |
| EXISTING LEGISLATION: |
|
Purpose |
Chapter |
Session |
Account |
Appropriation |
Due Date |
|
|
Level I |
8 |
1995 |
I |
$100,000 |
1996 |
|
|
Level II |
46 |
1997 |
I |
$175,000 |
1998 |
|
PROJECT INFORMATION:
Growth in the city and the surrounding area prompted the city to request
analysis of their problems. The rural areas around Lander typically
obtain their water from wells, which are of poor quality and quantity,
or they haul their water from Lander. Several areas, including Tweed
Lane, south of Lander, northeast of Lander, and Baldwin Creek, have
approached the city requesting water service. However, the city was
uncertain whether their system could reliably meet these and other future
water service demands. A Level I master plan was completed to serve as
a planning tool to respond to these requests.
The Level I study assessed the physical and economical limits of the
existing system to serve an expanded service area. The study determined
the water supply needs of that area, and evaluated the capability of
Lander's existing water supply to meet those needs. The study made
recommendations regarding the upgrading that will be required before the
city can serve the rural areas. The study developed preliminary designs
and cost estimates for the facilities identified as needing improvements.
The city prioritized the system improvements and requested a Level II
evaluation of the supply line to the treatment plant, enlargement of the
treatment plant, and additional storage at the treatment plant and near
the city. The Level II study recommended that the intake facilities be
improved and provisions made to handle the course sediments that enter
the water supply line from the river. The estimated cost of the
improvements is $400,000.
RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends that the project be advanced to Level III status in
the Rehabilitation Program with a 1999 appropriation of $200,000. The
financing plan includes a 50% grant, $200,000.00. The remaining 50% or
the loan portion will be the responsibility of the city from their sources.
|