Agency Information
Mission Statement
Directory
Calendar
Commission Agendas & Minutes
Consultant Selection
Items Open for Public Comment
Newsletter
Operating Criteria
Project Application Information
Send Us Your Comments
Planning Program
Dam and Reservoir Planning
Groundwater Grant Projects
Instream Flow Filings
Current Planning Projects
River Basin Planning
Weather Modification Study
Probable Maximum Precipitation
Water Research Projects
Construction Program
Current Construction Projects
Small Water Projects
Agency Publications
Project Reports
Water/Climate Web Atlas
Irrigation & Water System Surveys
Legislative Reports
Water Mgmnt & Conservation Dir
History of Wyoming Water Law
WWDC Home Page
Water Plan Home Page
WRDS Home Page
|
1999 LEGISLATIVE REPORT
Active Projects
59. | PROJECT: | Laramie Transmission Pipeline and Pioneer Canal Diversion | | | | | |
| LEVEL: | III |
| SPONSOR: | City of Laramie |
| LOCATION: | Albany County |
| PROGRAM: | Rehabilitation |
| |
| EXISTING LEGISLATION: |
|
Purpose |
Chapter |
Session |
Account |
Appropriation |
Due Date |
|
|
Level III |
38 |
1998 |
II |
$4,945,000 |
2002 |
|
PROJECT INFORMATION:
During the 1996-1997 Level III rehabilitation program it was discovered that
the severity of the corrosion 36" diameter transmission pipeline was not as
extensive as was anticipated, therefore, this pipeline will not need to be
replaced. However, the corrosion of the 24" transmission pipeline was
discovered to be worse than what was documented in the 1995 Level II study.
This pipeline will now need to be replaced. This project is currently under
design with the start of construction anticipated in the spring of 1999 and
completion for the fall of 2000.
The second component of this project is to rehabilitate the Laramie River
Pioneer Canal Diversion structure to accommodate winter flows. Recent growth
and population projects require the city to operate its water treatment plant
on a year round basis. Presently winter flows to the treatment plant are
measured by installing a temporary flume which is plagued by icing conditions.
This project will provide a permanent solution to diverting and measuring the
flows which will improve the winter time operation. This part of the project
is under construction and, barring unforeseen obstacles will be complete in
February, 1999.
RECOMMENDED LEGISLATIVE ACTION:
No legislative action required.
|