Agency Information
Mission Statement
Directory
Calendar
Commission Agendas & Minutes
Consultant Selection
Items Open for Public Comment
Newsletter
Operating Criteria
Project Application Information
Send Us Your Comments
Planning Program
Dam and Reservoir Planning
Groundwater Grant Projects
Instream Flow Filings
Current Planning Projects
River Basin Planning
Weather Modification Study
Probable Maximum Precipitation
Water Research Projects
Construction Program
Current Construction Projects
Small Water Projects
Agency Publications
Project Reports
Water/Climate Web Atlas
Irrigation & Water System Surveys
Legislative Reports
Water Mgmnt & Conservation Dir
History of Wyoming Water Law
WWDC Home Page
Water Plan Home Page
WRDS Home Page
|
1999 LEGISLATIVE REPORT
Active Projects
71. | PROJECT: | Midvale Sand Mesa Pipeline | | | | | |
| LEVEL: | III |
| SPONSOR: | Midvale Irrigation District |
| LOCATION: | Fremont County |
| PROGRAM: | Rehabilitation |
| |
| EXISTING LEGISLATION: |
|
Purpose |
Chapter |
Session |
Account |
Appropriation |
Due Date |
|
|
Level III |
206 |
1995 |
II |
$3,000,000* |
1997 |
|
| *100% grant for invoiced materials. The sponsor is responsible for all other project costs. |
PROJECT INFORMATION:
The Midvale Irrigation District serves about 73,000 acres irrigated by
about 700 individual irrigators. There is one incorporated
municipality, Pavillion, within the district. The assessments range
from $14.50 to $16.05/acre depending on the class of the land.
Irrigators within the district typically grow high value crops such as
sugar beets, beans, barley, corn and alfalfa hay.
The project was one of the identified options in the Wind River planning
efforts that could reduce diversion requirements and increase efficiency
by saving water that presently exits the district as operational waste
or as flow from the drainage system. The project will conserve 22,000
acre-feet of water by constructing approximately 66,000 lineal feet of
pipe. The savings will be realized by delivering irrigation water
through gravity pressured pipelines rather than the traditional open
canals. The water savings will provide increased carryover in Bull
Lake Reservoir or reduced direct flow diversions from the Wind River.
Construction of the project is about 99% complete. The new pipeline
was tested in the fall of 1998 and will deliver water beginning
with the 1999 irrigation season.
RECOMMENDED LEGISLATIVE ACTION:
No legislative action is required on this project.
|