Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
green drop bullet Mission Statement
green drop bullet Directory
green drop bullet Calendar
green drop bullet Commission Agendas & Minutes
green drop bullet Consultant Selection
green drop bullet Items Open for Public Comment
green drop bullet Newsletter
green drop bullet Operating Criteria
green drop bullet Project Application Information
green drop bullet Send Us Your Comments

Planning Program
green drop bullet Dam and Reservoir Planning
green drop bullet Groundwater Grant Projects
green drop bullet Instream Flow Filings
green drop bullet Current Planning Projects
green drop bullet River Basin Planning
green drop bullet Weather Modification Study
green drop bullet Probable Maximum Precipitation
green drop bullet Water Research Projects

Construction Program
green drop bullet Current Construction Projects
green drop bullet Small Water Projects

Agency Publications
green drop bullet Project Reports
green drop bullet Water/Climate Web Atlas
green drop bullet Irrigation & Water System Surveys
green drop bullet Legislative Reports
green drop bullet Water Mgmnt & Conservation Dir
green drop bullet History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

2000 LEGISLATIVE REPORT
Active Projects

 38. PROJECT:Gillette Storage & East End Transmission Improvements
LEVEL:III
SPONSOR:City of Gillette
LOCATION:Campbell County
PROGRAM:New Development
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level III 38 1998 I $2,040,000* 2002
*60% grant

PROJECT INFORMATION:
The City of Gillette is accelerating construction of the recommended Phase III improvements, as identified in the Gillette Area Master Plan. The new storage reservoir will allow the city to meet maximum daily demands and provide sufficient fire flows. This reservoir will provide two days of storage if the 43 mile long Madison pipeline was to be out of service.

Construction of the east end transmission pipeline will complete a major loop in the city's transmission system and will provide needed fire protection to this area of town. This improvement was also identified in the Gillette Area Master Plan.

This project is nearly complete. The line was finished in the early summer of 1999 and only minor work remains on the new storage tank.

RECOMMENDED LEGISLATIVE ACTION:
No legislative action required.