Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
green drop bullet Mission Statement
green drop bullet Directory
green drop bullet Calendar
green drop bullet Commission Agendas & Minutes
green drop bullet Consultant Selection
green drop bullet Items Open for Public Comment
green drop bullet Newsletter
green drop bullet Operating Criteria
green drop bullet Project Application Information
green drop bullet Send Us Your Comments

Planning Program
green drop bullet Dam and Reservoir Planning
green drop bullet Groundwater Grant Projects
green drop bullet Instream Flow Filings
green drop bullet Current Planning Projects
green drop bullet River Basin Planning
green drop bullet Weather Modification Study
green drop bullet Probable Maximum Precipitation
green drop bullet Water Research Projects

Construction Program
green drop bullet Current Construction Projects
green drop bullet Small Water Projects

Agency Publications
green drop bullet Project Reports
green drop bullet Water/Climate Web Atlas
green drop bullet Irrigation & Water System Surveys
green drop bullet Legislative Reports
green drop bullet Water Mgmnt & Conservation Dir
green drop bullet History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

2000 LEGISLATIVE REPORT
Active Projects

 79. PROJECT:North Cheyenne Master Plan
LEVEL:II-Hold
SPONSOR:Laramie County Commission
LOCATION:Laramie County
PROGRAM:New Development
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level II 10 1994 I Hold   1996
Level II 15 1996 I Hold   1998
Level II 82 1998 I Hold* 2000
*A total appropriation of $15,000 is available for hold projects.

PROJECT INFORMATION:
Water levels in domestic and stock wells in the north Cheyenne area have been decreasing. There are approximately 1,500 residences in the North Cheyenne area with a population of approximately 5,000 people. The area encompasses approximately 30 square miles. All the residences are served by individual wells and waste water is treated with individual septic systems. In 1991, the Laramie County Commissioners requested a Level I planning study to develop a master plan for the North Cheyenne area. The request was initiated in response to complaints of residents concerning reduced water levels in wells and possible water quality degradation.

In 1992, the WWDC contracted with States West Water Resources Corporation (States West) to complete a Level I water supply master plan study of the North Cheyenne area. The study was completed in 1993 and identified several water supply alternatives. Reconnaissance level designs and cost estimates were prepared for a system that would utilize groundwater as a water source, a rural water supply system with transmission capacity to address future growth using water supplied by the Cheyenne Board of Public Utilities, and a water supply system with limited transmission capacity using water supplied by the Cheyenne Board of Public Utilities. In addition, water conservation, aquifer recharge and no action alternatives were also evaluated. The Level I report concluded that the preferred alternative is to purchase water from the City of Cheyenne and to systematically construct a transmission pipeline system to accommodate existing and future water supply needs. The cost for the water supply system built to City of Cheyenne standards is about $45 per household per month. In addition, each landowner would have to finance approximately $14,000 for completion of a distribution system and connection to the main water supply lines.

The project was terminated at the conclusion of the Phase I work program because several issues (annexation, property owner interest) had to be resolved before additional technical work can be performed. In all probability, the interest in the project will vary throughout the area and the ultimate project will be phased based upon that interest.

RECOMMENDED LEGISLATIVE ACTION:
The Commission recommends the project be retained at Level II-Hold status.