Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
green drop bullet Mission Statement
green drop bullet Directory
green drop bullet Calendar
green drop bullet Commission Agendas & Minutes
green drop bullet Consultant Selection
green drop bullet Items Open for Public Comment
green drop bullet Newsletter
green drop bullet Operating Criteria
green drop bullet Project Application Information
green drop bullet Send Us Your Comments

Planning Program
green drop bullet Dam and Reservoir Planning
green drop bullet Groundwater Grant Projects
green drop bullet Instream Flow Filings
green drop bullet Current Planning Projects
green drop bullet River Basin Planning
green drop bullet Weather Modification Study
green drop bullet Probable Maximum Precipitation
green drop bullet Water Research Projects

Construction Program
green drop bullet Current Construction Projects
green drop bullet Small Water Projects

Agency Publications
green drop bullet Project Reports
green drop bullet Water/Climate Web Atlas
green drop bullet Irrigation & Water System Surveys
green drop bullet Legislative Reports
green drop bullet Water Mgmnt & Conservation Dir
green drop bullet History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

2000 LEGISLATIVE REPORT
Active Projects

 98. PROJECT:Sheridan Raw Water Supply
LEVEL:II
SPONSOR:City of Sheridan
LOCATION:Sheridan County
PROGRAM:New Development
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level III 16 1999 I $686,000 2002

PROJECT INFORMATION:
The City of Sheridan presently irrigates the Sheridan Cemetery with treated water from the city system. This causes an unnecessary demand on the treatment and delivery system. The city has acquired and transferred a water right to a potential diversion point on Big Goose Creek adjacent to the cemetery. The Joint Powers Board and the city are required under the Twin Lakes Reservoir 404 Permit to install water conservation measures. This project will conserve treated water and help address the permit condition. The study looked at the feasibility of constructing a diversion, pump plant and transmission line to convey water from Big Goose Creek to the cemetery. The total estimated cost of the project is $1,143,300.

RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends that the project funding be increased by $110,000 from $686,000 to $796,000 in the form of a $110,000 grant. The remainder is the responsibility of the city.