Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
green drop bullet Mission Statement
green drop bullet Directory
green drop bullet Calendar
green drop bullet Commission Agendas & Minutes
green drop bullet Consultant Selection
green drop bullet Items Open for Public Comment
green drop bullet Newsletter
green drop bullet Operating Criteria
green drop bullet Project Application Information
green drop bullet Send Us Your Comments

Planning Program
green drop bullet Dam and Reservoir Planning
green drop bullet Groundwater Grant Projects
green drop bullet Instream Flow Filings
green drop bullet Current Planning Projects
green drop bullet River Basin Planning
green drop bullet Weather Modification Study
green drop bullet Probable Maximum Precipitation
green drop bullet Water Research Projects

Construction Program
green drop bullet Current Construction Projects
green drop bullet Small Water Projects

Agency Publications
green drop bullet Project Reports
green drop bullet Water/Climate Web Atlas
green drop bullet Irrigation & Water System Surveys
green drop bullet Legislative Reports
green drop bullet Water Mgmnt & Conservation Dir
green drop bullet History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

2002 LEGISLATIVE REPORT
Active Projects

 38. PROJECT:Encampment Raw Water Line
LEVEL:III
SPONSOR:Town of Encampment
LOCATION:Carbon County
PROGRAM:Rehabilitation
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level II 60 1982 I $150,000 1983
Level III* 52 1984 I $60,000 1985
Level IV** 167 1985 1 $200,000 ***
Level III 2 2001 II $60,000 2005
*Level III in 1984 included only development of final plans and specifications.
**Level IV in 1985 included the authorization and funding of construction.
***Chapter 167 did not include a reversion date.

PROJECT INFORMATION:
The town of Encampment undertook construction of a new diversion facility and 1,800 feet of transmission line in 1986. Encampment would now like to pursue phase two of that project and enclose the remaining 6,200 feet of open ditch in a pipeline. The total project is estimated to cost about 800,000 The 2001 appropriation was for final design and specifications for the project. The sponsor has paid the loan portion of design expenses to date, so no loan funds have been disbursed during the design phase. The current request is for fifty percent ($400,000) of the funding to complete the project. Twenty-five percent ($200,000) of the project will be funded through RUS and twenty-five percent ($200,000) by the Town of Encampment using Capital Facilities Tax funds.

RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends the project be incorporated into the Rehabilitation Program at Level III with a 50% grant appropriation of $400,000.