Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
green drop bullet Mission Statement
green drop bullet Directory
green drop bullet Calendar
green drop bullet Commission Agendas & Minutes
green drop bullet Consultant Selection
green drop bullet Items Open for Public Comment
green drop bullet Newsletter
green drop bullet Operating Criteria
green drop bullet Project Application Information
green drop bullet Send Us Your Comments

Planning Program
green drop bullet Dam and Reservoir Planning
green drop bullet Groundwater Grant Projects
green drop bullet Instream Flow Filings
green drop bullet Current Planning Projects
green drop bullet River Basin Planning
green drop bullet Weather Modification Study
green drop bullet Probable Maximum Precipitation
green drop bullet Water Research Projects

Construction Program
green drop bullet Current Construction Projects
green drop bullet Small Water Projects

Agency Publications
green drop bullet Project Reports
green drop bullet Water/Climate Web Atlas
green drop bullet Irrigation & Water System Surveys
green drop bullet Legislative Reports
green drop bullet Water Mgmnt & Conservation Dir
green drop bullet History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

2002 LEGISLATIVE REPORT
Active Projects

 93. PROJECT:Pine Haven Madison Test Well
LEVEL:II
SPONSOR:Town of Pine Haven
LOCATION:Crook County
PROGRAM:New Development
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level I 36 2000 I $35,000 2001
Level III 2 2001 I $235,000 2004

PROJECT INFORMATION:
The "Town of Pine Haven Water System Master Plan," completed by Stetson Engineering in 2000, recommended that a second source supply well be developed as a system expansion alternative. The town currently has only one source of supply, the Keyhole No. 1 Well. If this well should fail, the community would be out of water as soon as the storage tank emptied. To increase the reliability of service to the water system, it would be advantageous to have a second supply well. A second well would provide system redundancy and provide additional capacity as the town develops in the future.

RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends the project be incorporated in the New Development program at Level II with an appropriation of $575,000 for test well drilling.