Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
green drop bullet Mission Statement
green drop bullet Directory
green drop bullet Calendar
green drop bullet Commission Agendas & Minutes
green drop bullet Consultant Selection
green drop bullet Items Open for Public Comment
green drop bullet Newsletter
green drop bullet Operating Criteria
green drop bullet Project Application Information
green drop bullet Send Us Your Comments

Planning Program
green drop bullet Dam and Reservoir Planning
green drop bullet Groundwater Grant Projects
green drop bullet Instream Flow Filings
green drop bullet Current Planning Projects
green drop bullet River Basin Planning
green drop bullet Weather Modification Study
green drop bullet Probable Maximum Precipitation
green drop bullet Water Research Projects

Construction Program
green drop bullet Current Construction Projects
green drop bullet Small Water Projects

Agency Publications
green drop bullet Project Reports
green drop bullet Water/Climate Web Atlas
green drop bullet Irrigation & Water System Surveys
green drop bullet Legislative Reports
green drop bullet Water Mgmnt & Conservation Dir
green drop bullet History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

2002 LEGISLATIVE REPORT
Active Projects

104.PROJECT:Riverton Valley Rehabilitation No. 2 - Phase I
LEVEL:II
SPONSOR:Riverton Valley Irrigation District
LOCATION:Fremont County
PROGRAM:Rehabilitation
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level II 86 2001 II $40,000 2002

PROJECT INFORMATION:
Flow measurements on the Riverton Valley Canal were conducted as part of the Wind River Basin study. The Riverton Valley open laterals experience high exfiltration as well as high maintenance costs. In 1994, the Commission recommended the project advance in the Rehabilitation Program to Level III status with an appropriation of $350,000. This project addressed twelve laterals under the main canal system. These open canals were replaced by buried pipelines, which greatly reduced maintenance costs and water losses. The district prioritized system repairs and work was completed in four phases from 1995 through the spring of 1999. The project appropriation served as a grant for project materials, with payments only being made for materials invoiced to the district. The district was responsible for all costs related to project design, permit procurement, land procurement, construction engineering and construction of the project. A total of 12 laterals were rehabilitated over a four year period from 1995 to 1999. The district has realized a 25% increase in delivery efficiency with the improvements made to date.

The Riverton Valley Irrigation District would like to rehabilitate a number of their laterals in an effort to continue their conservation program as specified in the WWDC Level I Report: Wind River Study: LeClair Canal and Riverton Valley (Wyoming No. 2 Canal Rehabilitation), March 1993; as updated by the Level II Report: Riverton Valley Rehabilitation No. 2, Level II, October, 2001. The 2001 Level II Report recommends the installation of pipe in nine additional open laterals and provided a revised estimate for rehabilitation costs totaling $670,000. The district funding request of $335,000 is for 50% of the project costs to be used for the purchase of materials. Engineering, installation and permitting costs are provided by the district.

RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends the project be incorporated in the Rehabilitation program at Level III with an appropriation of $335,000.