Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
green drop bullet Mission Statement
green drop bullet Directory
green drop bullet Calendar
green drop bullet Commission Agendas & Minutes
green drop bullet Consultant Selection
green drop bullet Items Open for Public Comment
green drop bullet Newsletter
green drop bullet Operating Criteria
green drop bullet Project Application Information
green drop bullet Send Us Your Comments

Planning Program
green drop bullet Dam and Reservoir Planning
green drop bullet Groundwater Grant Projects
green drop bullet Instream Flow Filings
green drop bullet Current Planning Projects
green drop bullet River Basin Planning
green drop bullet Weather Modification Study
green drop bullet Probable Maximum Precipitation
green drop bullet Water Research Projects

Construction Program
green drop bullet Current Construction Projects
green drop bullet Small Water Projects

Agency Publications
green drop bullet Project Reports
green drop bullet Water/Climate Web Atlas
green drop bullet Irrigation & Water System Surveys
green drop bullet Legislative Reports
green drop bullet Water Mgmnt & Conservation Dir
green drop bullet History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

2002 LEGISLATIVE REPORT
Active Projects

135.PROJECT:Wheatland Sand Lake Dam/Cañon Canal Rehabilitation
LEVEL:III
SPONSOR:Wheatland Irrigation District
LOCATION:Carbon, Albany, and Platte Counties
PROGRAM:Rehabilitation
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level I 15 1996 I $200,000   1998
Level III 38 1998 II $475,000* 2002
*50% grant, 50% loan (6%, 25 years)

PROJECT INFORMATION:
The Wheatland Irrigation District received a loan and grant appropriation of $475,000 for eligible project expenses. The purpose of the project is to repair the breach of the Sand Lake Dam, armor the spillway, install a telemetry monitoring system at Sand Lake, repair the Dutton Creek Reservoir outlet pipe, replace Dutton Canal concrete lining, stabilize the Cañon Canal slide area, install concrete lining in Cañon Canal along I-80, replace and install check and turnout structures and install appurtenances as necessary.

Construction of all project components except Sand Lake is complete. Repairs to Sand Lake Dam were bid in 2001 and bids exceeded available funding. Because of the location of Sand Lake and the July 1, 2002 reversion date for project funding, there is no time left available to construct the repairs. The current request is for additional funding and additional time to allow re-bidding the contract and hopefully having it constructed in 2002.

RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends the reversion date for project funding be amended to be July 1, 2006. The WWDC recommends the appropriation for project funding be amended to be $632,000. The financing plan is a 50% grant, $316,000 and a 50% loan, $316,000, for twenty-five years at 6.00% interest.