Agency Information
Mission Statement
Directory
Calendar
Commission Agendas & Minutes
Consultant Selection
Items Open for Public Comment
Newsletter
Operating Criteria
Project Application Information
Send Us Your Comments
Planning Program
Dam and Reservoir Planning
Groundwater Grant Projects
Instream Flow Filings
Current Planning Projects
River Basin Planning
Weather Modification Study
Probable Maximum Precipitation
Water Research Projects
Construction Program
Current Construction Projects
Small Water Projects
Agency Publications
Project Reports
Water/Climate Web Atlas
Irrigation & Water System Surveys
Legislative Reports
Water Mgmnt & Conservation Dir
History of Wyoming Water Law
WWDC Home Page
Water Plan Home Page
WRDS Home Page
|
2003 LEGISLATIVE REPORT
Active Projects
93. | PROJECT: | Pine Bluffs Supply/Pine Bluffs Brule Formation Water Supply | | | | | |
| LEVEL: | III |
| SPONSOR: | Town of Pine Bluffs |
| LOCATION: | Laramie County |
| PROGRAM: | New Development |
| |
| EXISTING LEGISLATION: |
|
Purpose |
Chapter |
Session |
Account |
Appropriation |
Due Date |
|
|
Level I |
10 |
1994 |
I |
$75,000 |
1996 |
|
|
Level II |
8 |
1995 |
I |
$150,000 |
1996 |
|
|
Level III |
96 |
2000 |
I |
$1,245,000* |
2004 |
|
| *60% grant, 40% loan (7.25%, 20 years) |
PROJECT INFORMATION:
A Level I study funded by the WWDC recommended construction of a transmission line, which
would connect the town's wells directly to their storage tanks. This would accommodate
construction of a single disinfection system at the tank, rather than installing disinfection systems
at each well. In 1995, a Level II study also looked at rehabilitation of the town's existing wells,
and updated Level I results for constructing the above referenced transmission pipeline. A
subsequent Level III construction project replaced one well. The 2000 Level III appropriation will
fund construction of the "wells to storage" transmission line that allowed the town to more
efficiently disinfect their water supply.
Construction of the transmission pipeline and appurtenances is underway with completion of the
project anticipated in 2003.
During the summer of 2002, the Town of Pine Bluffs experienced critical water shortages due to
extreme drought conditions. Substantial decline in the water table of the Brule Formation aquifer
has been experienced in all wells in southeastern Laramie County. The Town's Municipal Well
#5 has failed and the town procured WWDC Ground Water Exploration Grant funding in Fall
2002 to drill a replacement well. A successful test well was discovered and will serve as a
replacement well for Well #5. The Level III funding request is for assistance to install pumping
equipment and tie the new well into the town system.
-
Estimated Level III Costs
Final Designs & Specifications | $ 22,000 |
Permitting & Mitigation | 5,000 |
Legal Fees | 5,000 |
Project Components | $171,000 |
Engineering (12%) | 17,100 |
Construction Cost (Subtotal) | $ 188,100 |
Contingency (15%) | 28,215 |
Construction Cost Total (Subtotal) | $ 216,315 |
Project Total Construction Cost | $248,315 |
Rounded Total Cost | $250,000 |
RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends the project be incorporated into the Rehabilitation Program at Level III
with an appropriation of $250,000. The financing plan includes a 50% grant, and a 50% loan at
6% interest for 30 years.
|