Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
green drop bullet Mission Statement
green drop bullet Directory
green drop bullet Calendar
green drop bullet Commission Agendas & Minutes
green drop bullet Consultant Selection
green drop bullet Items Open for Public Comment
green drop bullet Newsletter
green drop bullet Operating Criteria
green drop bullet Project Application Information
green drop bullet Send Us Your Comments

Planning Program
green drop bullet Dam and Reservoir Planning
green drop bullet Groundwater Grant Projects
green drop bullet Instream Flow Filings
green drop bullet Current Planning Projects
green drop bullet River Basin Planning
green drop bullet Weather Modification Study
green drop bullet Probable Maximum Precipitation
green drop bullet Water Research Projects

Construction Program
green drop bullet Current Construction Projects
green drop bullet Small Water Projects

Agency Publications
green drop bullet Project Reports
green drop bullet Water/Climate Web Atlas
green drop bullet Irrigation & Water System Surveys
green drop bullet Legislative Reports
green drop bullet Water Mgmnt & Conservation Dir
green drop bullet History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

2003 LEGISLATIVE REPORT
Active Projects

 93. PROJECT:Pine Bluffs Supply/Pine Bluffs Brule Formation Water Supply
LEVEL:III
SPONSOR:Town of Pine Bluffs
LOCATION:Laramie County
PROGRAM:New Development
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level I 10 1994 I $75,000   1996
Level II 8 1995 I $150,000   1996
Level III 96 2000 I $1,245,000* 2004
*60% grant, 40% loan (7.25%, 20 years)

PROJECT INFORMATION:
A Level I study funded by the WWDC recommended construction of a transmission line, which would connect the town's wells directly to their storage tanks. This would accommodate construction of a single disinfection system at the tank, rather than installing disinfection systems at each well. In 1995, a Level II study also looked at rehabilitation of the town's existing wells, and updated Level I results for constructing the above referenced transmission pipeline. A subsequent Level III construction project replaced one well. The 2000 Level III appropriation will fund construction of the "wells to storage" transmission line that allowed the town to more efficiently disinfect their water supply.

Construction of the transmission pipeline and appurtenances is underway with completion of the project anticipated in 2003.

During the summer of 2002, the Town of Pine Bluffs experienced critical water shortages due to extreme drought conditions. Substantial decline in the water table of the Brule Formation aquifer has been experienced in all wells in southeastern Laramie County. The Town's Municipal Well #5 has failed and the town procured WWDC Ground Water Exploration Grant funding in Fall 2002 to drill a replacement well. A successful test well was discovered and will serve as a replacement well for Well #5. The Level III funding request is for assistance to install pumping equipment and tie the new well into the town system.

Estimated Level III Costs
Final Designs & Specifications$ 22,000
Permitting & Mitigation5,000
Legal Fees5,000
Project Components$171,000
Engineering (12%)17,100
Construction Cost (Subtotal)$ 188,100
Contingency (15%)28,215
Construction Cost Total (Subtotal)$ 216,315
Project Total Construction Cost$248,315
Rounded Total Cost$250,000

RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends the project be incorporated into the Rehabilitation Program at Level III with an appropriation of $250,000. The financing plan includes a 50% grant, and a 50% loan at 6% interest for 30 years.