Citizen    Government    Business    Visitor
Wyoming Water Development Commission 
Harry C. LaBonde, Jr., PE, Director 
6920 Yellowtail Rd, Cheyenne, WY 82002 
Phone: 307-777-7626 

Agency Information
green drop bullet Mission Statement
green drop bullet Directory
green drop bullet Calendar
green drop bullet Commission Agendas & Minutes
green drop bullet Consultant Selection
green drop bullet Items Open for Public Comment
green drop bullet Newsletter
green drop bullet Operating Criteria
green drop bullet Project Application Information
green drop bullet Send Us Your Comments

Planning Program
green drop bullet Dam and Reservoir Planning
green drop bullet Groundwater Grant Projects
green drop bullet Instream Flow Filings
green drop bullet Current Planning Projects
green drop bullet River Basin Planning
green drop bullet Weather Modification Study
green drop bullet Probable Maximum Precipitation
green drop bullet Water Research Projects

Construction Program
green drop bullet Current Construction Projects
green drop bullet Small Water Projects

Agency Publications
green drop bullet Project Reports
green drop bullet Water/Climate Web Atlas
green drop bullet Irrigation & Water System Surveys
green drop bullet Legislative Reports
green drop bullet Water Mgmnt & Conservation Dir
green drop bullet History of Wyoming Water Law

WWDC Home Page

Water Plan Home Page

WRDS Home Page

2003 LEGISLATIVE REPORT
Active Projects

 104. PROJECT:Ranchester Master Plan
LEVEL:I
SPONSOR:Town of Ranchester, Incorporated Municipality
LOCATION:Sheridan
PROGRAM:Rehabilitation
  
EXISTING LEGISLATION:
Purpose Chapter Session Account Appropriation Due Date
Level I 7 2002 II $75,000 2004

PROJECT INFORMATION:
The Town of Ranchester would like a feasibility and cost analysis of the recommendations outlined in the level I study completed in October 2002. These recommendations include evaluation of a new infiltration gallery upstream of Fivemile and Wolf Creeks, and further evaluation of water treatment processes used for taste and odor control and disinfection. The scope of work is contingent on the success of the Dayton well that is currently being drilled. If an adequate supply is found, Ranchester's needs will be met with a regional pipeline supplied by the Dayton well. The study would then be downsized to only address conveyance issues, emergency power issues and water storage issues.

RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends the project be incorporated into the Rehabilitation Program at Level II with an appropriation of $80,000.