PROJECT INFORMATION:
The Shoshone ID would like to continue the rehabilitation on the drop structures on the Garland
Canal. This is a large-scale project involving 4 drop structures and a drop structure combined with a
diversion. Also included are the control works on the Ralston Reservoir and conversion of
approximately 1.5 miles of ditch to a pressurized pipeline. The district plans to perform all
construction work.
RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends the project be incorporated in the Rehabilitation Program at Level III with
an appropriation of $570,000. The financing plan is a 50% grant, of $570,000, with the remaining
50% to be provided by the sponsor.