Agency Information
Mission Statement
Directory
Calendar
Commission Agendas & Minutes
Consultant Selection
Items Open for Public Comment
Newsletter
Operating Criteria
Project Application Information
Send Us Your Comments
Planning Program
Dam and Reservoir Planning
Groundwater Grant Projects
Instream Flow Filings
Current Planning Projects
River Basin Planning
Weather Modification Study
Probable Maximum Precipitation
Water Research Projects
Construction Program
Current Construction Projects
Small Water Projects
Agency Publications
Project Reports
Water/Climate Web Atlas
Irrigation & Water System Surveys
Legislative Reports
Water Mgmnt & Conservation Dir
History of Wyoming Water Law
WWDC Home Page
Water Plan Home Page
WRDS Home Page
|
2003 LEGISLATIVE REPORT
Active Projects
20. | PROJECT: | CAID Rehabilitation | | | | | |
| LEVEL: | New Application |
| SPONSOR: | Casper-Alcova Irrigation District |
| LOCATION: | Natrona County |
| PROGRAM: | Rehabilitation |
PROJECT INFORMATION:
The proposed project includes rehabilitation of Tunnel 3 and Tunnel 4 on the Casper Canal.
These tunnels are concrete lined with concrete transitions to the earthen canal. Cracking and
deterioration of the concrete lining and transitions resulting in heaves and voids are the primary
items to correct. These tunnels are relatively high in the water delivery system and are therefore
extremely important to the irrigators to keep in service. The proposed project would help assure
water delivery to the irrigators and keep the irrigation district in good standing with the US
Bureau of Reclamation, which owns the facilities. The project has been estimated to cost
approximately $170,000.
RECOMMENDED LEGISLATIVE ACTION:
The WWDC recommends the project be incorporated in the Rehabilitation Program at Level III
with an appropriation of $170,000. The financing plan is a 50% grant, $85,000 and a 50% loan,
$85,000, amortized over thirty years at 6.00% interest.
|